Retrospective Meeting: Metrics & Techniques

What is the Retrospective Meeting and what happens during the ceremony? A retrospective is a time-boxed ceremony where the Core Scrum Team (optional for the Product Owner) convenes to discuss the iteration that was most recently completed. This practice is very similar to the lessons learned meeting that takes place in waterfall projects. Pertinent information is collected during these meetings and is documented for utilization in future Sprints. Scrum Team members discuss their existing best practices, potential improvements, issues and blockages. The Scrum Master ensures that the high priority recommendations are implemented not later than the next Sprint.

The retrospective is an Inspect and Adapt event that is facilitated by the Scrum Master. Discussions, based on what went right and what went wrong, are recorded for imminent accomplishment. Participation by all team members is expected. The main goals of the retrospective are to provide responses for three distinct assessments:

  1. What are the things that the Scrum team needs to continue doing?
  2. What are the things that the Scrum team needs to start doing?
  3. What are the things that the Scrum team need to stop doing?

Retrospective Meeting: Metrics and Measuring Techniques

There are a variety of metrics that a Scrum team can utilize to measure their performance on a Sprint by Sprint basis. These metrics have been identified in Table 1. below.

MetricDescription
VelocityThe number of story points completed in a specific Sprint.  
Completed Success RateThe percentage of story points that have been completed compared to the commitment made by the team.  
Estimation AccuracyThe number or percentage of variations between projected and actual time spent on tasks and user stories.  
Feedback RatingsThe feedback obtained from stakeholders using subjective or objective ratings and providing a measurement of team performance.  
Team Morale RatingsThe outcomes from self-assessments concerning team member morale levels.  
Peer FeedbackThe methods used to obtain constructive feedback to provide understanding about team performance.  
Release ProgressThe business value provided in each release that increases the motivation levels of the team and work satisfaction.  

Table 1. Retrospective Metrics

Retrospective Meeting: Velocity

Velocity is a number that stands for the average number of user stories that have been completed during the Sprints. When a Scrum team has determined the average number of story points that they can complete, they can then calculate the estimated time frame that it will take to finish the project. The team will use the number of user stories that need to be completed and then divide this number among the remaining Sprints. For example, if a team has a total of 150 story points remaining, then the projection for completion is then 9. This assumes that the average velocity has been averaged at 17 story points per Sprint.

  • Team A has completed the following number of story points during the Sprints:
    • Sprint 1 – 15 story points
    • Sprint 2 – 16 story points
    • Sprint 3 – 20 story points
    • Average of Sprints 1,2,3 = 15+16+20 = 51/3 = 17 is the velocity
  • Story Points Remaining / Velocity = Number of Iterations Remaining
    • 150/17 = 8.82 = 9
  • It will take 9 Sprints to complete 150 story points based on the team’s projected velocity of 8.82

Retrospective Meeting: Completed Success Rate

This metric is represented as a percentage of the story points completed based on what the team projected that they would complete. For example, if the team made a commitment to complete 50 story points and they only completed 49, the completed success rate would be 49/50 = 98%.

Retrospective Meeting: Estimation Accuracy

This metric is represented as a percentage of the actual time spent on tasks and user stories and the time that the team estimated would be needed. For example, if the team estimated their total work as 50 hours and it took 45 hours to complete, then 45/50 = 90% estimation accuracy.

Feedback Ratings

This metric is the feedback rating from the stakeholders on the project using subjective and/or objective ratings that measures the Scrum Team’s performance. For example, stakeholder may provide feedback as “Very Good, Excellent, or Outstanding”.  This would be a subjective measurement of feedback. On the other hand, if a stakeholder responds on a scale of 1 to 5, where:

  • 1 = Outstanding (A)
  • 2 = Very Good (B)
  • 3 = Good (C)
  • 4 = Fair (D)
  • 5 = Poor (F)

The above measurement represents an objective feedback rating.

Our Favourite Agile Books

We found these books great for finding out more information on Agile Scrum:

Team Morale Ratings

The Scrum Team members conduct self-assessments regarding their morale in relationship to the project. For example, team members provide information such as:

  • Team Member 1 morale = High
  • Team Member 2 morale = Low
  • Team Member 3 morale = High

Peer Feedback

This metric is used to provide feedback for Scrum team members where each team member chooses a peer, conducts observation during an agreed upon time frame and then share the information to the selected peer. With Scrum, other members of the Core Scrum Team can participate in peer feedback (Scrum Master, Product Owner). Some firms use the 360-degree feedback model, a many-to-many feedback format. This model focuses on development team member performance evaluation and a questionnaire is typically used. This model has little to no team collaboration.

Release Progress

This metric is based on the amount of business value that is provided in each release based on story points. A Release Burnup Chart is used to identify the work completed for the release. A business uses this metric to determine how much work has been delivered. Burndown Charts can also be used for this metric.

In conclusion, companies have their organizational specific measurement techniques and metrics. The metrics presented here are just examples used during the Retrospective meetings and the choice of which ones to used are based on the Agile project’s needs.

The ‘Agile Scrum Master Training Course With 59 Seconds Training‘ is now available for free. This free Scrum Master Certified Online Training Course provides an in-depth understanding of the Agile Scrum Master roles and responsibilities, where you find out what a Scrum Master does and how to do it. During this free course you will learn all of the tools needed to succeed as an Agile Scrum Master.

Thank you for choosing us to learn about the Agile Scrum Framework.